Customer request:
The column must be switched to new operating modes with minimal modification of the internals.
Spliteks solution:
  • Analysis of the new column operating modes and assessment of the operability of the existing column internals
  • Report and recommendations on partial replacement of the column internals
  • Engineering
  • Manufacturing at the facility in Serpukhov
  • Delivery of the batch to the customer’s site
  • Installation supervision at the customer’s site and advice during commissioning
Result
Production of the required volumes of on-spec products with minimal changes to the internals design

Other Spliteks solutions

Installation
Customer request:
Manufacturing and supply of column internals for three phases of a stable gas condensate fractionation and transshipment complex at the port. Urgent supply and installation of column internals for the damaged main fractionator of Phase 2
Learn more
Integrated solution
Customer request:
Upgrading deethaniser 2/ZOK-1 to increase its capacity by 20% above the design capacity while ensuring that the total mass fraction of methane and ethane in the deethanised condensate does not exceed 0.8%:
Learn more
Replacement of obsolete equipment (column internals) dating from 1975
Customer request:
Obsolete equipment (column internals) dating from 1975 must be replaced.
Learn more
Increasing product draw-offs
Customer request:
Increasing the draw-off of the fourth vacuum side cut from column K-5 of the CDU/VDU-6 unit and improving its quality (reducing the colorimeter colour reading) while increasing the tar viscosity to approximately 300 mm²/s or higher, Improving fractionation sharpness and optimising operation of the wash section in vacuum column K-5 of the CDU/VDU-6 unit.
Learn more