Customer request:

Urgent diagnostics are required following an emergency pressure surge in the column, together with replacement of the damaged internals of the atmospheric column at the CDU/VDU unit.

Spliteks solution:
  • Design and engineering
  • Expedited manufacturing at the facility in Serpukhov
  • Delivery of the batch to the customer’s site

Result
Supply of 40 tonnes of column internals within 1 month after order placement